Welcome to ProjeQtOr new Forum. We migrated old forum to the new website.
You will find all your posts here, with your usual account.
Just one point : you’ll have to reinitialize your password. Use “Lost password” feature.
ProjeQtOr use priorities from 999 (lowest) to 1 (highest) while MS-Project is reverse: 0 (lowest) to 1000 (highest). ProjeQtOr export to MS-Project XML keeps ProjeQtOr priority definition instead of translating it to MS-Project one.
Expected behaviour is :
- ProjeQtOr priority 1 becomes MS-Project priority 1000, or probably preferably 999
- ProjeQtOr priority 999 becomes MS-Project priority 0, or probably preferably 1
Thanks.
Workaround :
* Copy the *priority* column in a spreadsheet
* Add a column with formula to reverse the priority : B2 = 1000 - A2
* Propagate for all lines
* Copy past the resulting column in MS-Project