Hello all,
when you book time on an activity, the left time decreases at the activity. You can see the left time at ‘real work allocated’ or also at the activity for every assignment. And if there is no time left, there is just a ‘0’. But then when you set the status of the activity to ‘completed’ the left time returns to the actual assigned time. (You can see in the picture)
For us this must be a bug. The time should remain ‘0’ when the activity is completed because there is no more time left.
Regards
Hi,
Behavior is confirmed.
This is a real issue and will be fixed asap.
Luckily, it is only the display that is wrong.
Data is correctly stored and not changed...
So issue is not so major as it appeared at first sight
Fix will be included in patch V6.4.3