Hello,
I use projeqtor 4.1.2 and setup a per resource calendar. When I set days off on the default calendar and go to imputation page, the days off are marked grey and that's fine, but when I do the same on a resource calendar, the imputation page does not change. Is it an issue or is there a way to really attach resource imputation to its calendar ?
thanks,
Stéphane
Adding an off day in the defualt calendar do not include it automatically into all others calendars.
You have to manually import default calendar into each calendar. Fortunately, there is a button to do this.
thanks for your answer babynus, but the issue is in the other way :
If I add a day off in a resource calendar, this day is not "gray" in the imputation page for this resource.
Stéphane
You're right Stephane,
Only defaut calendar is taken into account to display off days.
It is OK for planning (where multiple resouces are concerned), but on real work allocation, calendar taken into account should be the one linked to the resource.
Ticket #1335 recorded
thanks ! that's fine