Plan calculation failure in 8.4.0.

2 Posts
2 Users
0 Reactions
2,029 Views
(@hbarel)
Posts: 3
Active Member
Topic starter
 
[#6567]

In 8.4.0., re-calcing the plan causes failures of many Activities which cannot be scheduled. The error is: "There is ... days left to plan after resource allocation end date"
After analyzing it, I found that the problem stems from that resource allocation to projects does not get inherited properly.
Normally, a person/resource is allocated to a project if he is allocated to that project or to a parent.
However, in 8.4.0., for a resource to be properly allocated to a project for planning, he needs to be allocated to that project directly, and to every parent on the chain.
I do not think it is intentional.
Does anyone else see this phenomenon?


 
Posted : 18 Mar 2020 17H08
(@babynus)
Posts: 14952
Member Admin
 

This issue is fixed on V8.4.1


 
Posted : 20 Mar 2020 11H43