Hello guys!
When I run the report for project expense per month (costs -> project expense per month), the planned work (planned project expense) is never calculated although I've entered planned amount for a project expense. - The yellow field within this report is always empty.
The real work is correctly calculated on the real amount of the entered project expense.
Unfortunatly I can not attach a screenshot to this post 🙁
Can you reprduce this issue or is it my fault?
Regards,
Christian
I cannot reproduce.
When I add some project Expense (in Finantial => Project Expense), it is displayed on the report.
You can send print screen at support@toolware.fr
The planned expense as well?
I have sent you my screenshots.
The planned value is not displayed when a real value exists for the expense !
This is to be able to get a sum that will reflect reality as near as possible : real expense when exists, planned when not exists, and avoid counting twice an expense (as planned and as real).
Every report dealing with planned and reals works this way.
For instance the "work planned" and "detailed monthly plannig" reports work this way.