Dear,

We faced with issue from Timesheet: it seems planned work has been recorded automatically to all people assigned from january 1st, up to the end of the plan.
How can it be possible, how can we parameter that it never happens further?

By the way we still don't undestand how planned work displayed into timesheet is calculated. So we hide it. Values doesn't equal to the plan we think about. Could you explain us?

Thanks & regards,

 


 
Posted : 05 Jan 2021 16H10
Flou
 Flou
(@flou)
Posts: 253
Active Member
 

Hello,

on global parameter, on automation does the "Automatic actual supply" field have the value "yes"?

The planned work displayed into timesheet corresponds to the planned work of a person on an Activity( or an other element), the unity for your timesheet it's the same as the unit of workload ?


 
Posted : 05 Jan 2021 18H26
(@julien-gahon)
Posts: 20
Active Member
Topic starter
 

I see "alimentation automatique du réél" in "oui". Does it mean it put work planned asa we calculate the planning?


 
Posted : 06 Jan 2021 15H58
(@babynus)
Posts: 14952
Member Admin
 

It replaces planned with real for all past planning (planned days before current day)


 
Posted : 06 Jan 2021 16H41
(@julien-gahon)
Posts: 20
Active Member
Topic starter
 

Ok, so I keep it set "yes".
Into Global Parameter / Activity, there is "Manual Planned Interventions enter work as" : "planned" or "real". What does it mean and control?


 
Posted : 07 Jan 2021 16H24
(@babynus)
Posts: 14952
Member Admin
 

It's only for planning mode "Manual Planning"
 

With this planning mode, you use a dedicated screen, with calendar view, to defined work.
 

This can be "planned work" (that will need to be validated on timesheet) or "real work" (like for absence) depending on the parameter.


 
Posted : 07 Jan 2021 20H39