pools are lacking in the resource list of work plan per resource and per week

2 Posts
2 Users
0 Reactions
1,393 Views
(@brasal)
Posts: 52
Active Member
Topic starter
 
[#9246]

Hi,

In the report "work plan per resource and per week", the resource list does not contain resource pools. This is not the same behaviour nor expected one like in the planning per resource where pools planning are available along with real resource ones. Nevertheless, I would prefer that pools be redistributed in real resources in reports and in resource planning (cf this request). I have not tested other reports.


 
Posted : 18 Jan 2024 16H22
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

I would prefer that pools be redistributed in real resources

It is possible only if you select "Unique resource" in assignment for pools.
Then you get what you mant.


 
Posted : 30 Jan 2024 13H25