Reports/Costs/Resource costs per month

3 Posts
2 Users
0 Reactions
1,060 Views
(@laurentc)
Posts: 100
Active Member
Topic starter
 
[#8802]

Hi team,
In the resource costs per month, without any resource selected and without any month selected (=> all resources on one year):
Blue bars = planned + real => what is the interest? => The real values should be used in place of real+planned.
Black line: should be the cumulated value of blue bars, but is not.

Best regards,
#L.


 
Posted : 10 Mar 2023 11H06
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

If you edit the report in the middle of the month, you'll have have the month as Real work, and the other half ar Planned work.
You may also have some real work in the future (for holidays)


 
Posted : 10 Mar 2023 18H20
(@laurentc)
Posts: 100
Active Member
Topic starter
 

Thanks for your reply,
I understand what you're explaining, but still no catch the interest of [planned+real] blue bars.
And the cumulative black line is false, unless I'm wrong ?
Best regards


 
Posted : 13 Mar 2023 11H00