[SOLVED] Calculation of workload

4 Posts
3 Users
0 Reactions
2,135 Views
(@brunof782)
Posts: 45
Active Member
Topic starter
 
[#7538]

Hello,

i would to suggest you what seems to be a bug (v9.1.3). I have a projeqt with validated work and when i use the report "rapports / charges consommés / synthèse des activités par charge" (sorry not sure of the labels in english), i have this result : 

 

The total is 22,5 j but if made the calcul manually i have : 1 + 1 + 0,25 + 3 + 2 + 2 + 10,25 = 19,5.

Did i miss something ? Thanks for your help.
 


 
Posted : 12 May 2021 12H43
Damian
(@damian-sd)
Posts: 119
Active Member Admin Registered
 

Hello,

Indeed after recount validated work sum its not good,
we create ticket #5506 to fixe this.


 
Posted : 12 May 2021 19H04
babynus
(@babynus)
Posts: 14957
Main Contributor Admin
 

Hi,
This report only writes what is stored on items, so I don't think there may be an issue.
Maybe validated work on project sums some items that are not visible.
For instance, if you did not check "show visible items" closed tasks are not visible but thay are summed up on the project.


 
Posted : 14 May 2021 13H59
(@brunof782)
Posts: 45
Active Member
Topic starter
 

Hello,

you were right i had an activity that was closed with 3 days of validated work. 

thanks for the answers to both of you.


 