[Solved] Creator and changer of milestones is not able to set target date

3 Posts
2 Users
0 Reactions
1,737 Views
(@robra81)
Posts: 106
Active Member
Topic starter
 
[#7947]

Hello,
I gave the project team the right to create and change milestones but they are note able to set the target date (input field not editable) - did I forget to set one specific right for them?

Thanks
Ronny


 
Posted : 07 Dec 2021 8H21
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

You can change the "validated" target date, but not the "Planned" target date (wich is calculated)
So you must give these users capacity to change the validated data (it is a specific access right)


 
Posted : 09 Dec 2021 11H30
(@robra81)
Posts: 106
Active Member
Topic starter
 

That works! Thank you very much!!


 
Posted : 09 Dec 2021 11H41