Hi,

On projeqtor 11.4.0, in a "Time & Materials" project, a resource has assigned work on an activity and he is the only assigned resource. The activity has then been changed to state "closed". In gantt view "planning by resource", the closed date is 09/10/2024. In standard planning screen, the closed date is 26/09/2024. The project has been recalculated before and after without showing any change. Why is there two different "closed date" ?

Thanks a lot 
F.


 
Posted : 02 Oct 2024 18H19
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Is there any real work entered on the Activity ?


 
Posted : 10 Oct 2024 18H37
(@fsobel)
Posts: 20
Active Member
Topic starter
 

Yes, there is.
I check today and now both views are identical. So I close the subject on my side until further new notice of such effect.
Thanks a lot.
F.


 