In the Gantt chart, there is an option to display the resource name against the element's bar.
But this feature expects that each task is shared by a few resources.
But this assumption is belied when it comes to meetings: There are too many attendees to display.
As a result, the Gantt chart for a meeting shows a jumbled list of attendees.
(See task #7.1.10)
Desired: Show an asterisk in place of names. When the user hovers his mouse there, show all names.
Request recorded as Ticket #3404
NB : if you choose to display initials instead of full names, issue does not appear.
(this may be a workaround