Hi,
When i'm printing a time sheet to pdf, i have no issue, the time entered is displayed correctly
But when i'm exporting to EXCEL the time entered in time sheet is different in excel export
for example,
the activity "production des P&D conception" in PDF format it shows 6 hours
but in excel output it shows 0,8 hours
So is it normal ?
If yes, can you tell me the formula to convert 0.8 hours in Excel export to the actual 6 hours worked.
Where does this 0,8 hours come from ?
Regards
Export shows work in days.
6 hours = 0,8 day
Great ! Thank you