[v6.0.1 acceptance review] - 45° curve bug

3 Posts
2 Users
0 Reactions
7,580 Views
(@verges)
Posts: 85
Active Member
Topic starter
 
[#3921]

Hello,

As you can see in the file attached, a milestone line (the orange one) appears below the "bijectrice" line.

thanks.


 
Posted : 13 Dec 2016 18H13
babynus
(@babynus)
Posts: 14953
Main Contributor Admin
 

It can be a real use case, showing soe anomaly in the planning : it means that at a given date, the milstones has a planned end date before the current date and was not done yet.
This can happen if the milstone was not replanned or if it is (or was at this date) a "fixed milestone".


 
Posted : 13 Dec 2016 18H20
(@verges)
Posts: 85
Active Member
Topic starter
 

Yes, exactly 😉


 
Posted : 15 Dec 2016 20H09