Report planning by month of resource, project, activities show bad next month

Well Babynus, I have no doubt about the high quality of the help desk ! Fred

10 years ago
Reply
Horizontal scrollbar is missing in the Planning screen

Hi Babynus, Yes, it works ! When reducing the standard zoom (CTRL + "-" with Firefox), the horizontal scrollbar is here. But with normal zoom (CT...

10 years ago
Reply
Horizontal scrollbar is missing in the Planning screen

Hi Babynus, My version of ProjeQtOr is 5.5.4. I use FireFox 49.0.2 on Windows 10 Pro IE 11 produce the same problem. You will find in attachme...

10 years ago
Topic
Reply
[SOLVED] Real work allocation - Bad allocation after input

Hi, Thanks for analysis. But I am the only one who use this instance of ProjeQtor. I'm the only user. I promise ! :huh: And I am not double... u...

10 years ago
Reply
[SOLVED] Real work allocation - Bad allocation after input

Hi Babynus, Here are some copies of the table "work" (renamed "pj_work", PJ for ProJeqtor) - 07/08 : the day just after the first creation of the...

10 years ago
Reply
[SOLVED] Real work allocation - Bad allocation after input

Hi, At first, for this 05/08/2016, I have 3 allocations (on 3 activities). - Soutien => 0,25 - Recette => 0.25 - Etudes => 0.5 The...

10 years ago
Topic
Replies: 1
Views: 4213
Topic
10 years ago
Replies: 1
Views: 4059
Reply
[SOLVED] Real work allocation - Bad allocation after input

Hi, I think my way to use ProjeQtOr is not quite correct. - I use only 1 project : the "master" project. And then, I use activities. - Since 2 week...

10 years ago
Reply
[SOLVED] Real work allocation - Bad allocation after input

If that can help, here is the main screen of this activity :

10 years ago
Reply
[SOLVED] Report "monthly planning resource/project/activity"

Hi, Perhaps I found the reason why. In the Planning screen, after a clic on "Calculate activities planning" then planned work disapear on past days ...

10 years ago
Topic
Reply
In which industry do you use projector / Dans quel secteur d'activité utilisez vous projector

Hi, I work as a consultant in a little IT consulting firm. I use Projeqtor in my daily work with clients to planifer my work and activities.

10 years ago
Topic
Reply
[SOLVED] Since 5.1.0, activity status seems to be blocked

YESSSSSSSSSSSSSSSSS !!!!!!!! :woohoo: IT'S WORK !!! Thanks Babynus ! Without logs, I think it was difficult to find where was the error... The...

11 years ago
Reply
[SOLVED] Since 5.1.0, activity status seems to be blocked

Hi Babynus, Here is my last logfile : - open ProjeQtOr with my login (fga) as CP (profile) - open activity #135 - try to move status from Accepted...

11 years ago
Reply
[SOLVED] Since 5.1.0, activity status seems to be blocked

Hello Babynus, I've read all the messages of Damien. As a user, I have the CP (chef de projet) profile, which is already used in the workflows. By ...

11 years ago
Topic
Replies: 1
Views: 3285
Reply
[SOLVED] Since 5.1.0, activity status seems to be blocked

Hi, Babynus, Happy New Year, and all my bests 2016 wishes for you, your family, your projects (and... "The" Project ! B) ) My problems are sti...

11 years ago
Reply
[SOLVED] Since 5.1.0, activity status seems to be blocked

Hi Babynus, The activity type is "Task" and the workflow is "Default" So, anybody can change a task from "accepted" to "assigned" or from "in progre...

11 years ago