Hi Babynus,

I currently use the report "Planning > monthly planning resource/project/activity" to follow my daily activities.
But planned work are added to real work.
So the sum of each day and each activity is not good.

Is it possible to hide planned work to see only real work in reports ?
And in the future, having an option like in the "real work allocation" screen, with the "show planned work" check box ?

Or is it possible to have a new report in "real work" section, like the monthly planning, with only real work of each day.
Because (and I'm shure I'm not the only one) I need to report my activities each month to my office.
So, this is a very useful report.

Thanks a lot !
Fred


 
Posted : 19 Aug 2016 14H13
FredGarde
(@fredparis)
Posts: 50
Active Member
Topic starter
 

Hi,
Perhaps I found the reason why.
In the Planning screen, after a clic on "Calculate activities planning" then planned work disapear on past days (but non on future days).

Is it the good way to proceed ?
Thanks for your help,
Fred


 
Posted : 19 Aug 2016 16H11
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Request recorded as Ticket #2274


 
Posted : 19 Aug 2016 16H15
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Yes, if you recalculate planning, planned work deasepear.


 