Error planning calculation : unplanned work
Thanks for your quick answer. Just to be sure I set the right parameters at the right place: - in the resource page, I set every project rate at...
Il y a 7 ans
Forum
Error planning calculation : unplanned work
Ok. I understand that I cannot bypass it. Therefore, is there a way to know how to unblock this situation (I just know that these meetings are proble...
Il y a 7 ans
Forum
Error planning calculation : unplanned work
Hello I regularly have the same problem. What is the best process to determine where the issue comes from ? In my case, two 1 day meetings ca...