Meeting and "Following tasks could not be completely planned"

I read issue #3241 and that's my problem. I have meetings of one day but starting after the start hour of the day

8 years ago
Reply
Meeting and "Following tasks could not be completely planned"

We are using V6.5.2. We will update to V6.5.6 and then I'll get back to you. Thank you

8 years ago
Reply
Meeting and "Following tasks could not be completely planned"

The conflicting activity (planning mode is ASAP) is in the same project but not the same subproject. When rescheduling, I tried to select the root pr...