Hi, Thanks for your advise. Actually I would like to see the detail change history e.g. [Resource Name] , [Rate%], [Assigned (d)] when modified. I...
Hi, May you advise in what menu to click on the task to view the icon for the assignment details history? I went to the projects menu, activities m...
Hi, Would you advise how to view the record? Thanks, Rainbow
Hi Babynus, In my experience, the planning mode "Regular between dates" are mostly used for tasks with float which the project manager would like t...
Hi Babynus, Thanks for your reply. I agree that "Regular between dates" are supposed to be fixed tasks, which they should be constrained by the val...
I inputted the task and the resource info for the task mentioned as activity #580, validated start date = '2021-05-07' and validated end date = '2021-...
I searched in the DB with the following results which is the same as the work plan report. For resource D: For resource F:
Hi Babynus, I rechecked that there are no meetings or real work entered in May, which is why I found it weird. Thanks, Rainbow
Hi Babynus, Many thanks for your explanation on the calculation. I think the situation you mentioned does explain for some of the cases, while for ...
Hi Babynus, Thanks for your reply. Good to know that training courses would be helpful. Just want to check if the cases mentioned in previous po...
We'll think of a change that will set WBS for this "technical" project to zero, so it won't set the mess (as it's never visible on the Gantt) Many th...
Hi babynus, Yes, WBS should reflect the structure for any structure changes. Would you advise how to reorder the project with WBS 1 which is the de...
Hi, I removed attribute "required" on field "idProject" in model/DocumentMain.php and the control alert of project/product must be available. Ho...
Hi, Thanks for your reply. I understand that mostly the project related documents are the main target. Is it possible to at least add feature to en...
Thanks. It would be great for top management (e.g. superuser who have all view rights) of the organisation to be able to view all the resources in the...
Hi, Thanks for your reply. I saw that sorting by clicking on the column headers of object list is now available in V9.1.1 which is great, but I ...
Hi, I enabled all access rights for admin. I also tried to log in as another user with the same profile 'admin' and a few users shown in the limit ...
Hi, Thanks for your reply. It's good to know that direct column width for object list is on V9.1 and in the future on Gantt charts. I also would li...