Can you add a screen copy? Are users mentionned affected to the project? With which role?
Seems my tests were wrong. Rights on sub-project can be less than project. Sorry.
Thanks, but not sure to understand well your answer : if rights are inherited, I can't have less right on a subproject? I made some tests and it seems...
It seems that if you attach a sub-project to project P, field then becomes grey (which is normal). But if then you attach sub-project to another pr...
I found all these datas are managed in table 'planningelement', and for the project with problem, field ValidatedCalulated was '1'. I modified it in d...
I don't succed to reproduce this case on another project. Don't understand how I got this project in that state?? Could you tell me in which table a...
Thanks for answer, specially today! My question is not regarding cost (that I understood are consolidated from activities behind. I am speaking of pr...
Hi, Same question regarding project expenses : I indicated a value for project validated expenses on one project, but now field is grey and can't b...