A second that. From my point of view, the descriptions / labels are also confusing in the English translation. The section is called "Access to ...
Assignement is to define which resource will work on activity and with effort (work) is required to execute the activity. This will enable capacity p...
Great, thanks, that's it! I found the permission setting and was able to enable the subscription button for my user. Now I just have to test it / p...
Mh, I had a look at the "Access Rights" screen, but it is still not obvious to me - which permission exactly do I have to activate such that a normal ...
Thanks for your quick reply, the "email on event" feature looks pretty powerful! Is there a way to subscribe to an Item like a Ticket such that I g...
And, another question: What happens with Tickets which are not assigned to any Activity? How (if at all) are those considered during planning, ...
However this means that Activities estimated to take only 1 or 2 hours cannot be used in planning as such - for planning, they will always take at lea...
Thanks for your answer. How can I deal with Acitivities which will only take about a few hours at most? You can : just enter assigned work as hour...
Thanks a lot for your answer! 🙂
Thanks for your reply. Unfortunately, I'm not quite sure if we understood each other correctly. All you need to do is go to the global parameter...