We extended API of PQ by method allowing us to encrypt passed text. It was the easiest way for us.
And this is the problem I think many persons reported on the forum. Projeqtor uses PHP library for AES:CTR create by Chris Veness This library uses it...
Thanks, solution works perfectly. By the way, seems on 7.0.2 changing order of columns (at least on Activity view) is no longer working. Additiona...
Hello, I found one issue more which can refers to problem described above. Of course we appliyed scripts you listed and all practically is working...
Yes, you have right, I was not enough precise. If in the project I have 2 resoruces with rights to validate real_work (settings validation_real_wor...
Hello, How can I navigate to issue of given numer (in this case 3231) to check state of it ?
But if on TOP level rights are "X" and on sublevel I extend them or change them to "Y" what then ? User has superposition of X, Y ? Only Y ?
Hi, Base on this picture again: Activities from top have IDs: 1. 1442 2. 2098 3. 2079 I did not find any other way to export history...
But how access rights on project 2 levels upper can impact rights on direct project ?
Well, indeed, I cannot reproduce this case on demo installation however I can do that 100/100 on our system. I have no any dates as start / end dat...