Hello, I finally found where was the left work. It was in meetings that were not closed. Not a bug, I close the issue.
Hi again, I have an other task with similar problem. Once again, only 1 ressource assigned to the task, no more left work on the ressource. But thi...
Hi Pascal, Thanks for the quick reply. Effectively we were in case 2 => planning not recalculated for one of our projects.
Hello Pascal, Thanks for the quick reply. I Not a bug at all finally.
Hi, 1) How can we put/get correct data for future bills and payments ? I think that just enter bill, on some "prepared" status, with expected amou...
Hi, Thanks for the reply, I modified the file model/CommandMain.php with $work += $line->numberDays; and now it's working correctly (after havin...
Ok that's clear, thank you !
Hi Pascal, This works thank you !
Hi Pascal, Thanks for the answer. The workaround is working well. One more question, how can we put dates in start and end dates ? So I could u...