[SOLVED] Monthly ressources availability report strange reporting

3 Posts
2 Users
0 Reactions
1,810 Views
(@louisc)
Posts: 58
Active Member
Topic starter
 
[#7013]

Hello,
I have something strange in the Monthly ressources availability report.
For one of the ressources, it displays a negative number between -0,13 to -1 when there are between 1 and 8 hours entered in the imputations (1 day = 8 hours).
For all other ressources, the display is coherent (0 when 8 hours are entered in the imputations, positive number if less than 8 hours are entered in the imputations, and red negative number if more than 8 hours are entered in the imputations).

Can this be linked to planned tasks ? I'm not sure as only 1 ressource is impacted with this strange displaying...

Thanks for the answer.


 
Posted : 03 Nov 2020 16H28
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Negative availability means overuse.
This can occur in two cases :
1) someone calculated a project with overuse feature on
2) resource entered real work different from planned, and project planning is not recalculated (so real + pexisting planned is over capacity)


 
Posted : 03 Nov 2020 17H10
(@louisc)
Posts: 58
Active Member
Topic starter
 

Hi Pascal,

Thanks for the quick reply. Effectively we were in case 2 => planning not recalculated for one of our projects.


 
Posted : 03 Nov 2020 21H00