Hello, This is an interesting option, I couldn't find it, could you tell me where I can find it thank you,
Not corrected in 8.6.2 Please correct in next release
I found origin of problem : there is an E-E predecessor dependency on parent (Task 3014 have parent "Developpement" 3639) 3639 have predecessor End...
On task 3014, ressource is Faly NB : Project QUANTA VIEW 5.400 is a sub project of PROJECT "PROJET" On task 3653, ressource is Hery NB : ...
You can show that on capture on first post
No milestone linked to this task
Of course, at least 20 time since problem was discovered Planning is recalculated each day Same behaviour Thanks