Hi, Thanks for your sharing. I earlier have set both admin profile and manager of leave, and with "Administrator of leaves system" checked for a...
Noted. Thanks for your reply and advice.
I am using version 8.6.6
Hi, Thanks for your prompt advice. I ran the check and fix and have the error message as attached. My colleague have just requested to delete the p...
Hi, In that case is it possible to keep the assignment changes record in the database? Thanks, Rainbow
Hi, I would like to be able to view the assignment info history as below together with the planned dates and work calculated. Is it possible? ...
Hi, Thanks for your advise. Actually I would like to see the detail change history e.g. [Resource Name] , [Rate%], [Assigned (d)] when modified. I...
Hi, May you advise in what menu to click on the task to view the icon for the assignment details history? I went to the projects menu, activities m...
Hi, Would you advise how to view the record? Thanks, Rainbow
Hi Babynus, In my experience, the planning mode "Regular between dates" are mostly used for tasks with float which the project manager would like t...