Last seen: 31 Mar 2021 10H22
Exact. Just change the view and return on planning view activate the new item button. Many thanks.
I've clear the browser cache. Same problem. Find in attached file the browser console error message.
I've an administrator profile. No issue in the log file, just the connection trace. No actin when I click on the button (no menu like "create new pr...
So can you confirm availibilty report doesn't reflect the truth ? Is it possible to have a new evolution request : had a field to insert the departure...
Many thanks babynus. Everything works perfectly ! Evolution : is it possible to have a message when task can't be planned (with explanation) ?
Yes it's a resource view. Some of resources are affected on some tasks. Screenshot in attached file. Upgrade to v7.3.4 version --> no more b...
I'm administrator and the specific ressource is "Team member" Log file in attached file
Capacity of the ressource : 1 ETP Project assignment : 100% Task assignment : 1 day As you can see on the picture attached, some tasks don't have...
1) Fix planning isn't checked on project (and on project on superior level). 2) WBS structure seems correct. But Consistency Check report oan error a...
Hi, Yes I did. I run it today but still same problem. I've the same problem on differents projects. Same process to create project and task but on so...
New try today on another project. Creating a new task then assigning a ressource (and charge) to this task. Re calculate the project. Still no sche...
I've change left work --> still have the project icon center white. (not orange) Then i (re)calculate the planning --> still have the project i...