1-year working time...
 
Notifications
Clear all

1-year working time planning

8 Posts
2 Users
0 Reactions
5,414 Views
(@pgalland)
Posts: 4
Active Member
Topic starter
 
[#4074]

Is it possible to inform the availability of a team over 1 year and if so how?
thanks in advance


 
Posted : 06 Feb 2017 16H33
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Yes, with report "Planning" => "Availability synthésis"


 
Posted : 06 Feb 2017 16H36
(@pgalland)
Posts: 4
Active Member
Topic starter
 

Ok thanks, but my question is how to charge holiday periods in the software ?


 
Posted : 06 Feb 2017 17H33
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Enter real work on Administrative project.


 
Posted : 06 Feb 2017 17H33
(@pgalland)
Posts: 4
Active Member
Topic starter
 

As a new project?


 
Posted : 06 Feb 2017 17H39
(@pgalland)
Posts: 4
Active Member
Topic starter
 

In fact I already have a holiday schedule for my whole team. I would like to fill it out the calendar to dispose of my resource capacity over the year.


 
Posted : 06 Feb 2017 17H46
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

For generic off days, use calendar (you can use default one, that will be used on planning view). You can create new calendar for other specific iff days (for instance for resoucez working in different countries with own off days)
For individual off days, create new administrative project with one or several activities and enter real work in the future to enter off days)


 
Posted : 07 Feb 2017 22H25
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

For generic off days, use calendar (you can use default one, that will be used on planning view). You can create new calendar for other specific iff days (for instance for resoucez working in different countries with own off days)
For individual off days, create new administrative project with one or several activities and enter real work in the future to enter off days)


 
Posted : 08 Feb 2017 21H44