Access right for change activity status

2 Posts
2 Utilisateurs
0 Reactions
2,903 Vu
(@grenzini)
Posts: 1
New Member
Début du sujet
 
[#4710]

Hello,
I'm new wih Porjecqtor, I have one question please.
I have created a profile that is similar to the Project Leader but without all the financial section.
I have an issue in this profile, the users with this profile can not change the status of an activity.
I think that I have lost an access right somewhere, can someone tell me which is the access right to assign for permit the change of the status of an activity?

Thanks
Gabriele


 
Posté : 18 Oct PM 15:1010
(@babynus)
Posts: 14952
Membre Admin
 

You need to allow profile in the workflows.
Check workflows.

NB : when creating new profile looking like another one, crete new from copy and not from scratch, you'll retrieve correct configuration of source profile and will just have to update the differences.


 
Posté : 21 Oct AM 00:1010