Activity is cut
 
Notifications
Clear all

Activity is cut

3 Posts
2 Users
0 Reactions
3,630 Views
(@drubs2010)
Posts: 25
Active Member
Topic starter
 
[#1486]

Hello,

In this exemple, some activity is cut.

Why "Reprise des fichiers" has charge on tuesday and thursday?

There is only one ressource at 70% on the project. The activity "Développement PGM transco" is the predecessor of "tests unitaires pgm transco".

Others, "Reprise" and "Modification CL", have no predecessor.

This is the planning:

Thank you for your help,

Drubs2010.


 
Posted : 21 Nov 2013 19H20
(@babynus)
Posts: 14952
Member Admin
 

Could you give information about priority of the activities ?
It they are all the same, then planning seems normal, priority if given by WBS.

So "Développement PGM transco" is planned =>OK
Then "Modification CL" is planned, but cannot start on the sale day because of predecessor constraint.
Then "tests unitaires pgm transco" is planned => OK
Then "Reprise des fichiers" is planned. And as it has no constraint, it used the availability left on tuesday.

If you want to avoid this behavior, you must allow your task "Modification CL" to start same day as predecessor : set delay to -1 in the dependency definition.


 
Posted : 22 Nov 2013 2H19
(@drubs2010)
Posts: 25
Active Member
Topic starter
 

Thank you for this tip.

Regards,

Drubs2010.


 
Posted : 22 Nov 2013 17H06