After V8.4.2. Planned Dates Problem

3 Posts
2 Utilisateurs
0 Reactions
1,800 Vu
 Erki
(@kiroglu)
Posts: 13
Active Member
Début du sujet
 
[#6606]

Hello,
After updating to the last version, and calculating activities planning, activity date has become abnormal. Am i missing something?
As a note: i have used pool resource, assigned it to avtivities and also used "unique resource" option in another project.

Thank you for your efforts.


 
Posté : 2 Avr PM 21:044
 Erki
(@kiroglu)
Posts: 13
Active Member
Début du sujet
 

Hello again,
I spotted that the problem might be related to "not splitted work", because when i disabled that option of an activity, its planned date has become reasonable.


 
Posté : 2 Avr PM 22:044
(@babynus)
Posts: 14952
Membre Admin
 

Hi,

It you set "not splited work" and set limit to 1 (full time), it resource has some regular work, even for 0,1 day about once a week, the task will be postponed until a time frame is found where the resource can work 100% on the task without any (aven small) interuption.
Remove the constraint or lower the threshold so that calculation can consider that enven not full day is stil "not splitted"


 
Posté : 5 Avr PM 16:044