After V8.4.2. Planned Dates Problem

3 Posts
2 Users
0 Reactions
1,815 Views
 Erki
(@kiroglu)
Posts: 13
Active Member
Topic starter
 
[#6606]

Hello,
After updating to the last version, and calculating activities planning, activity date has become abnormal. Am i missing something?
As a note: i have used pool resource, assigned it to avtivities and also used "unique resource" option in another project.

Thank you for your efforts.


 
Posted : 02 Apr 2020 21H17
 Erki
(@kiroglu)
Posts: 13
Active Member
Topic starter
 

Hello again,
I spotted that the problem might be related to "not splitted work", because when i disabled that option of an activity, its planned date has become reasonable.


 
Posted : 02 Apr 2020 22H58
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Hi,

It you set "not splited work" and set limit to 1 (full time), it resource has some regular work, even for 0,1 day about once a week, the task will be postponed until a time frame is found where the resource can work 100% on the task without any (aven small) interuption.
Remove the constraint or lower the threshold so that calculation can consider that enven not full day is stil "not splitted"


 
Posted : 05 Apr 2020 16H03