Hello,
I think I don't know how to use this option "Auto update of left work on Pool" of global parameters (timesheet)
Even if a ressource of the pool enter real work with no left work, the left work of the pool is not automatically updated, it stays equal to the initial assigned work.
How can I achieve that the left work of the pool is set to 35.47 days in the attached image
?
Thanks in advance,
Hello, is your resource part of your pool?
I find it strange that your resource is on top of your pool.
What version are you on?
The option you indicate allows the remaining work in the pool to be decremented automatically when a resource (in the pool) no longer has any remaining work to do.
See this :
Have a nice day,
Hello,
Yes, the ressource is part of the pool.
I am using the version v1.11.2.
I don't know why the ressource is on top of my pool.
I have refreshed the work of the ressource directly in the timesheet, and today the left work of pool is automatically updated.
I am importing the real work from Excel to Projeqtor so maybe the left work on the Pool is not updated in this import.
Thanks a lot for your answer
Hello,
Yes, when you import work by "importing data", the Pool is not automatically decremented.
Ticket recorded #9976
Have a nice day,