Forum

Auto update of left...
 
Notifications
Retirer tout

Auto update of left work on Pool

4 Posts
2 Utilisateurs
0 Reactions
695 Vu
(@alr)
Posts: 4
Active Member
Début du sujet
 
[#9808]

Hello,

I think I don't know how to use this option "Auto update of left work on Pool" of global parameters (timesheet)
Even if a ressource of the pool enter real work with no left work, the left work of the pool is not automatically updated, it stays equal to the initial assigned work.

How can I achieve that the left work of the pool is set to 35.47 days in the attached image 

 

?

Thanks in advance,

 


 
Posté : 10/04/2025 3:25 pm
(@maxime)
Posts: 268
Membre Admin
 

Hello, is your resource part of your pool?
I find it strange that your resource is on top of your pool.
What version are you on?
The option you indicate allows the remaining work in the pool to be decremented automatically when a resource (in the pool) no longer has any remaining work to do.
See this :
 

 

 

Have a nice day,


 
Posté : 18/04/2025 10:51 am
(@alr)
Posts: 4
Active Member
Début du sujet
 

Hello,

Yes, the ressource is part of the pool.
I am using the version v1.11.2.

I don't know why the ressource is on top of my pool.

I have refreshed the work of the ressource directly in the timesheet, and today the left work of pool is automatically updated.

I am importing the real work from Excel to Projeqtor so maybe the left work on the Pool is not updated in this import.

Thanks a lot for your answer


 
Posté : 18/04/2025 1:42 pm
(@maxime)
Posts: 268
Membre Admin
 

Hello,
Yes, when you import work by "importing data", the Pool is not automatically decremented.
Ticket recorded #9976
Have a nice day,


 
Posté : 22/04/2025 12:44 pm
Share: