Dear all,

I'm preparing documents for a project and I'm facing an issue - probably due to my lack of knowledge of the tool.
I would like to assign "Material" type resources for:

  • Lab hour usage - I do suppose that this is the same as any human resource
  • One shot usage resource - like manufacturing of the prototype, that happen one or two times in the project.

With this information I need to create a cash-flow graph within the project timeline.

How am I able to insert the "shot" usage? Do I have to insert it as 1 day "work" assignment or is there a smarter way? (On MS-Project there is a kind of resource that allow such one-shot usage)

Then once the project is living, how do I insert the costs used for those material costs and therefore calculate what remains to be spent on the project?

Thank you


 
Posté : 11/02/2022 4:50 pm
(@babynus)
Posts: 14952
Membre Admin
 

Hi,

You have to manage materials like human resources.
If it is used 2 times in the project, you plan 2 days.
To manage costs, you enter daily cost for the resource.


 
Posté : 12/02/2022 7:38 pm
(@cmarti)
Posts: 65
Estimable Member
Début du sujet
 

Even if, coming from MS Project, the idea is not the most obvious, it is clearly a simple way to have the cost integrated correctly on the whole project.

So for having a cash-flow information on all but human resources, I suppose I can use the "Resource cost per month" report on a team or organization that will filter those resources.
or
Is there other reports to have the cash-out forecast?
And in this case how should I integrate external resources - consulting, ...?


 
Posté : 14/02/2022 10:07 am