Cannot close Activity - "Unable to close an element with left work"

7 Posts
2 Users
0 Reactions
5,394 Views
(@barrys)
Posts: 11
Active Member
Topic starter
 
[#1641]

I have an activity that has 2 assignments and one of the assignments (resource) has now left, the activity is complete even though it didn't take as much time as planned.

But it will not left me close this activity as there is "left work" - I have no idea how to close this - please see attached for the situation.


 
Posted : 22 Feb 2014 18H51
babynus
(@babynus)
Posts: 14954
Main Contributor Admin
 

Just edit the assignment and set left work to 0.
This can also be done throught the '"real work allocation" screen.

Then you can close the activity.


 
Posted : 22 Feb 2014 19H35
(@barrys)
Posts: 11
Active Member
Topic starter
 

Just edit the assignment and set left work to 0.
This can also be done throught the '"real work allocation" screen.

Then you can close the activity.

That is great - thanks - it worked in that case. NOw I have another case - but there are no assignments this time. Is there another advice you could favor me with please?


 
Posted : 22 Feb 2014 23H47
babynus
(@babynus)
Posts: 14954
Main Contributor Admin
 

I would need more detail.

What is the message ?


 
Posted : 23 Feb 2014 2H01
(@barrys)
Posts: 11
Active Member
Topic starter
 

I would need more detail.

What is the message ?

I did attach another picture - but it didn't sem to come through... other than this what information is appropriate
that you need?


 
Posted : 23 Feb 2014 12H55
(@barrys)
Posts: 11
Active Member
Topic starter
 

I would need more detail.

What is the message ?

Here is another picture and the message is the same... "Unable to close an element with left work"


 
Posted : 23 Feb 2014 12H58
babynus
(@babynus)
Posts: 14954
Main Contributor Admin
 

The picture is clear : you still have some left work (1 hour).
If you don't have an assignment on the activity, then possibly left work is on a daughter activity (activity with parent activity as current activity).
A glance at the planning view will help you see the hierarchic links.


 
Posted : 23 Feb 2014 14H20