Hello,
I would like to change "status" (from recorded to assigned, in order to make them visible for project memebers) for many activities.
To do this, I change status activity by activity. It takes time.
It would be interesting to select all of them and change status "in one click" 🙂 I don't think PrOjeqtOr manges that as for now ?
(we could imagine such treatments for other fields than status...)
Sincerely.
It would be interesting to select all of them and change status "in one click" 🙂 I don't think PrOjeqtOr manges that as for now ?
ProjeQtOr does ! :woohoo: :woohoo: :woohoo: :woohoo: :woohoo:
Just use the multiple update feature (button with several save disks)
(we could imagine such treatments for other fields than status...)
It also does ! :woohoo: :woohoo: :woohoo:
Maybe ProjeQtOr is better than your sweeter dreams :kiss:
Hello,
Thank you for your answer.
OK, I didn't know this functionality. Is it possible to select many activities with a shortcut (Shift, Ctrl...) ? Selecting hundred activities means 100 clicks...:unsure:
I was looking at it in Follow-up / planning and not in Work / activities, because it's easier working on the planning view with indentation than in the Activity view where it's difficult to work with all activities at the same level.
If you confirm there's no such icon in Planning view, I would have two sweet dreams B) :
- either adding the functionality in Planning mode
- either indenting a little in Activity mode
Iin fact, I realize that I'm wondering why there is 2 different views :
- the left panel of Planning mode (very legible and for me the main work area with PrOjeQtOr)
- the Activities view (not very legible in my humble opinion) which seems to me offering more or less the same functionalities
Sincerely.
Is it possible to select many activities with a shortcut (Shift, Ctrl...) ?
Filter activities so that you have all activities you want then click on icon check/uncheck (on button section).
- either adding the functionality in Planning mode
Will be difficul to add extra button as planning view already adds extrat indenting buttons.
either indenting a little in Activity mode
Not possible as list can be sorted, and ther indenting would mean nothing.
in fact, I realize that I'm wondering why there is 2 different views :
- the left panel of Planning mode (very legible and for me the main work area with PrOjeQtOr)
- the Activities view (not very legible in my humble opinion) which seems to me offering more or less the same functionalities
In fact planning is devoted to ... planning, and shows not only activities but also milstones, projects, meetings....
It is a very fluent view for building WBS of project, but not for all.
It does not allow filtering, sorting, displaying any filed of activity.
Activity screen does...