Hello,
I searched for a while, but I have found nothing equivalent to what I'd like to :
Is it possible to ensure that assignments have a start date and an end date? Or simply close a assignement ?
We have a case where a resource change function (result: new assignments). This resource use to have worked on several activities with its old function, so we cann't remove old assignments. So this resource has two lines for each activity in real work allocation, with a consequent risk to charge to the old line instead of the new one.
In the real work allocation, these assignments should no longer appear from termination or closing date.
Thank you for your response.
------------------------------------------------------
Bonjour,
J'ai cherché pendant un moment, mais je n'ai rien trouvé d'équivalent à ce que je souhaite :
Est-il possible de faire en sorte que les assignations aient une date de début et une date de fin ? Ou simplement clore une assignation ?
Nous avons un cas où une ressource change de fonction (conséquence : nouvelles assignations). Cette ressource avait des imputations sur plusieurs activités avec son ancienne fonction, donc nous ne pouvons pas supprimer les anciennes assignations. Cette ressource a donc deux lignes pour chaque activité dans la saisie des imputations, avec un risque conséquent d’imputer sur l’ancienne ligne au lieu de la nouvelle.
Dans la saisie des imputations, ces assignations n'apparaitraient donc plus à partir de leur date de fin ou de cloture.
Merci de votre réponse.
Hi,
No, there is no way to close an assignment.
Only setting left work to zero indicates assignmnent is complete (and it is then posible to hide assignment with no left work on Real Work Allocation)