Dear Expert,
can I copy sub-activity to multiple activities in the same project?
i.e. I have 18 activities under project 10 -> activity 10.1.
Now I want to repeat sub-activity 10.1.1 in each of the activities up to 10.18..
I will need to do the same task at least 6 times in the same project.
Posté : 8 Avr PM 17:044
No, There is no shortcut to do this.
It would have been easier to copy the parent tasks with its structure...