displacements ... Is there a way to enter the displacements? For example during the week there may be trips to collect aobjet or various appointments ... which are outside the project thank you
***
dépalcements...
y a t il une manière de rentrer les dépléacements ?
Par exemple dans la semaine il peut y avoir des déplacements pour récupération d'aobjet ou rdv divers ... qui sont hors projet
merci
Hello,
just in case it can help : we use 2 tips to handle business trips and off-projects stuff :
1/ Create a type of activity «Déplacement», so it is easy to identify activities of the project that are realized in the customer premises for instance.
2/ Create a project dedicated to all «diverse» stuff and unplanned activities such as overhead (corporate meetings, ...) or external training, etc ...
My 2 cents,
hi
manual planification or filing a line on timesheet screen which belongs to an administrive project type or the worst solution creating a meeting ( a special one as displacement )
Projeqtor do never give one single solution. Each user use it as he wants.
merci à tous