Hello

very good product 🙂
in the top !!
however I lack an element !!!

How to be able to extract the list of day / hours charged to a project? (Especially to change any earlier date)

is there a easy way to view the days of projects worked by a resource?

example:
A project start 2015/01/2016 end 2016/08/08

the project includes but extends 45 days worked by several resources?
How to extract the list from a project for each task associated with this project?
Example thomas resource was mistaken in the earlier date? and would like to change?

via imputation menu is week by week?
hard to find the time sheet in all projects?

2
est'il possible to have the same view Agenda over a year including all projects?
(The same view of such calendar that spans a year?
Thank you in advance for your help.


 
Posté : 8 Oct PM 13:1010
Klaus
(@climb4fun)
Posts: 449
Contributor
 

Hi Chris,

did you try the reports?

Regards,
Klaus


 
Posté : 10 Oct PM 12:1010
(@chriscool)
Posts: 63
Active Member
Début du sujet
 

I have found no report or to view
to list all the charges (charged by time resources) on a project about the activities!

DUCOUP for the resource itself, difficule founir of a report or find the time to make the change if we were wrong of hours or days

thank you in advance for your help if possible


 
Posté : 10 Oct PM 18:1010
Klaus
(@climb4fun)
Posts: 449
Contributor
 

Hi Chris,

in the menu, go to reports - real work - e. g. 'Detailed work per resource - monthly'

Regards,
Klaus


 
Posté : 10 Oct PM 18:1010
(@chriscool)
Posts: 63
Active Member
Début du sujet
 

Hello
i try on projeqtor demo with manager account
yes this report displays the total hours or days worked!
i like this repport for resume stats

but I need to know the date that were consomées day on each task.

I do not see the detail, for example

A resource ==> 4:00 on A task At the 25.08.2016 (and the resource may change the date of 25.08.2016 in 8 hours for example

Resource B ==> 8 hours on A Task 4 on 27/08/2016

on another tool other than projeqtor
I get the list of time spent on a task for resources
so I can go as a resource to change the time or day when I made a mistake
or as a manager have exact visibility


 
Posté : 10 Oct PM 18:1010
Klaus
(@climb4fun)
Posts: 449
Contributor
 

... and what's about`:: Report - Planning - Monthly planning resource/project/activity


 
Posté : 10 Oct PM 18:1010
(@chriscool)
Posts: 63
Active Member
Début du sujet
 

yes is better

can i per yearly ? its the best:-)


 
Posté : 10 Oct PM 18:1010
(@chriscool)
Posts: 63
Active Member
Début du sujet
 

yes is better

can i per yearly ? its the best:-)
Miss per YEARLY 🙁


 
Posté : 10 Oct PM 19:1010
Klaus
(@climb4fun)
Posts: 449
Contributor
 

Give a try to reports in 'real work'. There are yearly reports.


 
Posté : 11 Oct AM 11:1010
(@chriscool)
Posts: 63
Active Member
Début du sujet
 

yes thanks you
but i want same Monthly planning resource/project/activity

YEARLY planning resource/project/activity miss this option snif :- :cheer: 😛


 
Posté : 11 Oct PM 23:1010
(@babynus)
Posts: 14952
Membre Admin
 

Subject recorded as Ticket #2346


 
Posté : 12 Oct AM 10:1010
(@chriscool)
Posts: 63
Active Member
Début du sujet
 

Thank you for the support this feature
Planning yearly resource / project / activity