Hi
I try to find on the activity view or report, but I didn't find it. :blush:
Is it possible to display all tasks where an assigment exists but the assigned time is 0?
No,
Only possible to get activities where assigned work is zero.
But you'll also get activities with no assignment.
To get activities where assigned work is zero, what is the way?
Edit filter,
Select column "Assigned work"
Select operator "="
Enter value "0"
So filter will be "Assigned work=0" 😉
Thanks Babynus!!!
Just another question: If i have one task with 10hrs as work plan and all the time (10hrs) was consumed but the ressource need 5hrs more, the ressource need to add 5 hrs on the "Reste à Faire"? or it is not mandatory?
Yes it is required to have correct plannign.
Otherwise ProjeQtOr will not "guess" there is some left work and will consider tasks as done.
Ok, but the planning is recalculate automatically or not ?
No
So, How can I detect this update (to recalculate the planning)? With an alert? because I saw an red exclamation point (with this text: reassessed work compared to validated work) on the activity but no warning was displayed.
You can define an alert that will be triggered when Reassessed Work (Real+Left) > Validated Work.
Perfect, thanks a lot.