Question about planning and Planned End Date

5 Posts
3 Users
0 Reactions
3,335 Views
 
(@justsomeone)
Posts: 3
Active Member
Topic starter
 
[#2747]

Hello,

Would like to get some clarification on this situation:

Why is the planned end date at 01/10 instead of 18/09? You can see above that the only activity in the project just goes from 02/09 to 18/09 and I can't get why I get the planned end date after that period? Can someone shed some on this?

Thanks in advance.


 
Posted : 19 Nov 2015 19H18
 Dan
(@caccia)
Posts: 340
Contributor
 

Hello,
Most likely this is because you have 'real work' logged on 01/10.
The 'planned end date' is actually the max of 'initially planned end date' and 'real end date' => if someone actually did some work on that activity on 01/10, it cannot end before that date.

You should be able to check in the 'detailed work per resource' report if this is correct.

Cheers!


 
Posted : 23 Nov 2015 15H04
 
(@justsomeone)
Posts: 3
Active Member
Topic starter
 

Thanks for answering.

But that is not what is happening. The monthly detailed real work per resource is empty for October, reason why I don't understand why I get that 01/10 for planned end date. I just have a few days (6 total) in September.

Let me ask this question: If someone by mistake introduced real work to 01/10 even if by mistake and later removed, would that justify what is happening? (Not sure if this happened, just trying to understand why)


 
Posted : 23 Nov 2015 18H57
(@babynus)
Posts: 14952
Member Admin
 

Most likely :
you planned activity, that had plannig date to 01/10 (expected planned date)
then resource entered some real work up to 18/09, set left work to zero, and indicated task as done : so real end date was defined as last real work (18/09)
Since real end date is set, and no left work exist on the task, planned end date is not acutalized any more : it will alway stay to latest value.
It has no importance as real end date exists.


 
Posted : 23 Nov 2015 22H41
 
(@justsomeone)
Posts: 3
Active Member
Topic starter
 

Thank you for the answer.


 
Posted : 24 Nov 2015 14H43