Hi
We are working with PorjeQtor for more than one year .... and I'm stll be disturbed with the way the planification works.
I've a FIXED project with resources allocated on FIXED tasks.
If I press the calculator the "Nothing to plan" message pops up. Which is OK.
However the planned end date is moving forward. The real work is in late on this task. But, as the project is FIXED, the end planned date would not change.
Version used is 10.2.2.
Question:
Why the task is replanned despite the fixed planning mode ?
Best regards.
I cannot reproduce the behavior.
For me Fixed projects are never changed.
Possibly planned end date is changed from last real work entry (planned end date cannot be less that last actual entry)
... FIXED, but re-planned. I do confirm that we have this concern on several tasks.
It creates confusion.
Is there any workaround to stop any re calculation ?
Best regards,
#L.
Do these tasks are planned to end before current day ?
This may not be a recualculation, but just actualization of planned end date for tasks that "should have ended".
Please give more hint.
Screen shots, ...
Do these tasks are planned to end before current day ? => NO
This may not be a recualculation, but just actualization of planned end date for tasks that "should have ended". => Are you saying that in fixed planning the end-date is re-calculated ?
I'm trying to catch what did occur. I'll keep you informed.
Thanks in advance.
Best regards.