Reccurent task planning but not on an weekly baseline

5 Posts
3 Utilisateurs
0 Reactions
1,814 Vu
(@bvd)
Posts: 124
Estimable Member
Début du sujet
 
[#8811]

Hi,

Is there a way to plan a task on a specific period each month ?

For example :
- Team A does a task each month betwenn the 16th and the 21st day of the month.

I do not understand how to do this and the manual didn't help me


 
Posté : 17/03/2023 6:24 pm
(@babynus)
Posts: 14952
Membre Admin
 

No, no planning regular.
Only weekly regular exists.
you must plas a main task wuth sub-task for each period.


 
Posté : 20/03/2023 11:23 am
(@bvd)
Posts: 124
Estimable Member
Début du sujet
 

Ok thanks.

It would be great to be able to plan as regular periods 🙂


 
Posté : 22/03/2023 3:59 pm
(@lhullebr)
Posts: 17
Eminent Member
 

I also think that it would be helpful to plan with a periodicity (monthly, quartely or annualy)


 
Posté : 27/03/2023 6:39 pm
(@babynus)
Posts: 14952
Membre Admin
 

But this would be more complex to define an manage.
I know how to manager 0.5 day every friday : easy.
But manager 0.5 day the 10th of every month will be a mess : what should I do if it is a sunday ?
The only "easy way to define regular for months is "every 1st monday of the month" or "every last monday of the month" or "every first open day of the month" ...
It is not easy to define on a calendar basis, so much harder to define that weekly regular.

Moreover, montly frequency means you just have to define 12 times a year, so either you define an main activity with 12 subactivities, or just use a manually planned activity with 12 selections of periods...

So I see very small interest to manage so complex feature

 


 
Posté : 28/03/2023 1:38 pm