How can I do change cost on work

3 Posts
2 Users
0 Reactions
2,973 Views
Florent MOYER
(@fmoyer)
Posts: 26
Active Member
Topic starter
 
[#4313]

Hello,

In my enterprise, the change of cost of resources are been announcing at the end of month and It must be applied on the 1rst.
How can I do the change on the work already done ?

Thanks


 
Posted : 28 Apr 2017 18H44
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Just enter cost on resource for corresponding function.
Real cost will be updated from real work.


 
Posted : 29 Apr 2017 19H12
Florent MOYER
(@fmoyer)
Posts: 26
Active Member
Topic starter
 

OK thanks


 
Posted : 03 May 2017 16H03