Hello all;
My question concern the ressources's management. I create 2 dfferents projects with some activities and (with the same dates ans ressources) but no pop up or something else tell me that the ressources is use in the same time by two different projet.
I tried to be accurate and i hope that you understand my question 🙂
Have a good day all !
It is possible to affect resource so several projects at 100% at sema time.
Affectation will just give possibility to work on both.
So there is no message as there is no issue.
You can see global affectation rate on resource form.