Ressources
 
Notifications
Clear all

Ressources

4 Posts
2 Users
0 Reactions
2,819 Views
(@toulousevb)
Posts: 2
New Member
Topic starter
 
[#3409]

Peut on avoir un récapitulatif des imputations pour une seule ressource


 
Posted : 23 May 2016 15H08
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Please post in english


 
Posted : 23 May 2016 15H56
(@toulousevb)
Posts: 2
New Member
Topic starter
 

is it possible to have a sumary of all the activities of a ressource
for example :
ressource 1 : activity in charge = activity A and activity B
ressource 2 ==> activity A and activity C
i would want to have
for ressource A on may 23th = x hours on activity A and y hours on activity B
The must would be :
on may, 23th, ressource 1 has a time work of x+y and its normal time of work for a monday is z hours...
thank you for your answer


 
Posted : 23 May 2016 16H19
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Have a look at :
Report "Planing by Resource/Project/Activity"
Agenda view
Resource Planning view


 
Posted : 23 May 2016 20H53