Hi,
Would you advise on how to import organisation holiday and leave applied per employee? I would like to import the leave applied and approved from an HR system to projeqtor so that planning and timesheet entry can take into consideration of the leave approved. Thanks.
Thanks,
Rainbow
Posté : 4 Juin PM 13:066
Just have to use the Import process or API.
You must deal with object LeavePeriod