Notifications
Retirer tout
Ask questions
2
Posts
2
Utilisateurs
0
Reactions
1,533
Vu
Début du sujet
Hi,
Would you advise on how to import organisation holiday and leave applied per employee? I would like to import the leave applied and approved from an HR system to projeqtor so that planning and timesheet entry can take into consideration of the leave approved. Thanks.
Thanks,
Rainbow
Posté : 04/06/2023 1:56 pm
Just have to use the Import process or API.
You must deal with object LeavePeriod
Posté : 09/06/2023 5:26 pm